4/16/24: Installed Parking Signs
4/16/24: Stone Veneer Installed on Courtyard
4/16/24: Finished ADA Spaces
3/4/24: Completed and cleaned unit bathroom
3/4/24: Completed corridor
3/4/24: Completed and cleaned unit
2/26/24: Installed Additional Directional Signs
2/26/24: Guardrail Installed And Anchored
2/26/24: Finished Generator Enclosure
2/21/24: Completed Nurse Station 3
2/21/24: Directional signs Installed
2/21/24: Completed PT room
2/5/24: Completed training room
2/5/24: Living room
2/5/24: Completed bathroom
1/2/24: Dining room
1/2/24: Private dining room
1/2/24: Resident rooms
7/31/23: Patio sawcut and rock installed
7/31/23: Carpet installed in living room
7/31/23: Flooring completed in lobby
7/10/23: Flooring being installed
7/10/23: Entryway concrete has been poured
7/10/23: Finishing up the entryway
5/22/23: Nurse Call Lights Installed in Area D
5/22/23: Installing countertops in public areas
5/22/23: Kitchen equipment installed
5/22/23: Landscaping rock installed on North side of building
5/22/23: Rock installed at courtyard landscaping areas
5/22/23: Turning power on in building
10/19/22: Site Progress Aerial Photo
10/19/22: Site Progress Aerial Photo
10/19/22: Site Progress Aerial Photo
9/1/21: Site Progress Aerial Photo
8/1/21: Hanging corridor walls throughout building.
8/1/21: Site Progress Aerial Photo
6/7/21: Site Progress Aerial Photo
4/7/21: Felt underlayment for the clay roof
3/30/21: Site Progress Aerial Photo
2/15/21: Site Progress Aerial Photo
1/12/21: Site Progress Aerial Photo
1/10/21: Site Progress Aerial Photo
1/8/21: Building roof crickets and parapet walls
12/22/20: Site Progress Aerial Photo
12/11/20: Framing and roof joists down a hallway
12/7/20: Site Progress Aerial Photo
12/4/20: Framing of curved dining room wall
11/10/20: Site Progress Aerial Photo
11/6/20: Sheathing walls around Section D
10/30/20: Roof joists in Section B
10/30/20: Setting Steel for Porte Cochere
10/29/20: Setting Roof Joists in Section B
10/26/20: Site aerial photo
10/23/20: Plywood Sheathing for Shear Walls
9/29/20: Framing in Section B
9/28/20: Site Aerial
9/27/20: Part 2 of Section A slab
9/23/20: Curbs formed in Section B to be poured
9/18/20: Spread sand in Section A
9/15/20: Part two of concrete floor slab Section D
9/11/20: Vapor barrier & slab rebar in Section D
9/4/20: Rebar for footings in Section A
9/4/20: Part two of concrete floor slab in Section C
8/14/20: Poured concrete footings in Section C
8/7/20: Sand in Section B
7/31/20: Placing rebar for foundations in Section B
7/17/20: Layout for footings in Section C
7/10/20: Back filling onsite utility trenches
6/26/20: Continued installation of water sewer
6/19/20: Underground plumbing Section B
6/12/20: Backfilling and compaction of gutter lines
6/5/20: Site Progress Aerial Photo

CAREERS

UPDATE: We anticipate the completion of construction to be completed in Spring of 2025.

 We are pleased to offer career opportunities in a variety of departments from entry level to management – including Certified Nursing Assistants, Licensed Nurses, Nurse Managers, Dietary and Environmental Services. We work hard to ensure we hire the most qualified and professional individuals who understand the needs of our patients and residents and who will strive to meet our standards of excellence.

Benefits and rewards:

  • Health, dental and life insurance
  • Vacation, paid sick time, holiday pay
  • 401-K
  • Annual review

To apply, click the buttons below to download our Application & Applicant Reference Check Form.  Email them both back to info@DesertRidgeTCC.com